17 million rubles have been allocated for the preparation of Braslav for the regional "Dazhynki-2019". Education leads in the use of funds
In an online format, the heads of district services reported to the chairman of the district executive committee, Alexander Bodanin, on what had already been done. Together, they determined which facilities should be focused on in the near future, and what could be done without significant financial costs and project development.
The discussion covered bus stops, small architectural forms, directional signs, the creation of a stone park, and repairs in the private sector. By joining forces, homeowners and the communal service are re-roofing, painting facades and fences, and tidying up outbuildings.
As for major facilities, design and estimate documentation is currently being prepared for their current or capital repairs and construction, contractor selection procedures are underway, and in some places, work has already begun. The majority of the plans of the Braslav residents have found support from higher authorities, which is reflected in the funding – almost 17 million rubles have been allocated for the preparation of the rural workers' holiday.
17 million rubles allocated for the preparation of Braslav for "Dazhynki"
The most significant allocations will be directed to the education sector (4.7 million rubles), healthcare (2 million), the creation of a new recreation area along the beach and "Brukivka" (2 million), the construction of a sports and recreation complex (2 million), the renovation of the housing stock (1.8 million), the improvement of the city and its road network, and the repair of social sphere institutions and administrative buildings.
In addition, the acquisition of equipment for schools and kindergartens, and several school buses are planned.
The education department of the district executive committee is currently leading in the utilization of the allocated funds.
Last year, it began the capital repair of Secondary School No. 2 and Kindergarten No. 3. In the school, some windows were replaced, the foyer was redecorated, and classroom repairs were started.
In 2019, according to the head of the department Ivan Oborovich and the director of the educational institution Anatoly Neverkovich, the general contractor Polotskselstroy began the implementation of the developed repair work project for this year. The roof renovation continues, work has begun in the sports and assembly halls, and classrooms; rhythmics and martial arts halls will appear.
The most significant changes are planned for the school grounds. Three sports grounds will appear here: one of them is multifunctional – it will be possible to play volleyball and basketball, the second will be equipped with outdoor exercise equipment, an auto-town will appear for children to learn traffic rules, and a workout area for gymnastics enthusiasts. In front of the central entrance, which will also be redone, and on the side paths, tiles will be laid instead of asphalt pavement.
According to Anatoly Neverkovich, the total cost of the project is about 1.5 million rubles.
— We will truly become a "School of the Future," where all conditions will be created for the students. Equipment for chemistry classrooms, computer and language labs, a vocational training room have already been purchased, and new equipment will appear in almost all classrooms, which will contribute to improving the quality of education.
Last year, work also began in kindergarten No. 3, for the major renovation of which 1.8 million rubles were allocated. The walls were insulated, the roof was repaired, the floors on the first floor became warm, new beds and playgrounds were purchased. Next summer, young Braslav residents will be able to enjoy the new conditions in full.
At the concept development stage, the local authorities decided to use funds from the district and allocated by the region, taking into account the future perspective – to give Braslav its own unique character and increase the comfort of urban life. For this purpose, the design organization "Mastak-service" was invited to the staff meeting, the director of which acquainted those present with the specialists' proposals for the design of the district center.
The scope of work also requires the staff to strengthen control over the progress and timeliness of their implementation, and to coordinate the efforts and resources of the contractors. Time is pressing for everyone.